Saturday, May 29, 2010

Open Floorplan

A lot has been going on in the last few days. We had to take a mini-break to celebrate my birthday. Work was still happening, just at a slower rate.


Here's a picture of the window in the master bedroom that Jesse and Tanner framed in on Wednesday. There was a larger window there but it would have been in the way of the new bathroom wall...so bye bye old window.



Jesse worked on demo-ing the wall between the bathroom and the master bedroom -- He did half of it then I started working on the second half. Oooh! Open concept floor-plan!!!



I have to say that it felt pretty good to knock that wall down.



Jesse cleaned up after me. Here you can see the whole wall and linen closet have been removed. Pat stopped by around this time to give us a hand.



Here he is doing tall people work. Woo hoo Pat!!!



I worked on the details.



Who needs walls in their bathroom anyway?


Next up (hopefully finishing before tomorrow night):
Finish demolishing the bathroom
Build a temporary wall to support the load
Frame in the new bathroom walls and pocket door
Drywall one side of the walls for privacy

Next two weeks:
Plumbing and electrical

Then our first inspection on the new stuff!